Supply chain issues delay Virginia lawmakers’ move into new General Assembly office building

RICHMOND, Va. (WRIC) — State lawmakers won’t move into the Virginia General Assembly’s new office building in downtown Richmond for the 2023 session due to supply chain issues.

The problems “threaten to inhibit completion of the building in time to prepare for a successful legislative session” and will force lawmakers and their staffs to remain in the Pocahontas Building through till at least the end of the 2023 session, according to the Virginia Department of General Services.

The Department of General Services, the agency managing construction of the new 14-story-tall office building, said plans to have lawmakers in the building by mid-October were on schedule before the issues.

The agency said in a release that shipments of materials required for building code compliance and operations have been delayed, including audio and visual equipment for the assembly’s legislative work. Equipment needed for critical building code compliance testing has also been delayed.

“Like so many, I regret not being able to move in on time to the first purpose-built GAB for the public to more easily observe and actively participate in the law-making process,” Virginia House of Delegates Clerk G. Paul Nardo said in a statement. “Unfortunately, we simply are not immune to the delays, prolonged delivery schedules and other deferrals being experienced by so many across Virginia and around the country and world.”

Virginia Senate Clerk Susan Clarke Schaar said in a statement that “supply issues and COVID-19 have made major impacts on the process and we cannot at this time ensure a functional and complete building.”

The new General Assembly office building will have tunnels to connect it to a new parking deck at the corner of Broad and 9th streets and the Virginia State Capitol’s underground visitor’s center.

Construction of the office building began in 2019 and the Department of General Services says it is expected to be fully functional in early 2023.



Source link

RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular

Angels bring top prospect Logan O’Hoppe to taxi squad

ANAHEIM — The Angels didn’t bring catcher Logan O’Hoppe to Angel Stadium to play, but they still feel he can gain invaluable experience. The...

University of Florida student from Allegheny County describes preparing for Hurricane Ian

Lots of Pittsburghers have loved ones living in Florida. For one O’Hara Township family, their son is a first-year student at the University...

Northeast Ohio woman finds comfort in COVID long haul group therapy

Group therapy sessions help long COVID patients feel less isolated, while providing support from those who understand their suffering. ...

LA police chief says agency lacks resources for all mental health crisis calls

LOS ANGELES — Less than one-third of calls to the Los Angeles Police Department involving people experiencing a mental health crisis are being...

Recent Comments